STUDI KELAYAKAN BISNIS ( BUSINESS FEASIBILITY STUDY ) : PERT


III. P E R T

PERT: a method of analysis that was created to help thescheduling and supervision of projects that are complex and require certain activities to be performed in the order of a particular sequence.

incremental Cost

Is added as a result of the reduced cost of one unit of time.

COST Ic = Δ / Δ TIME = (Cc - Cn): (Tn - Tc)

Cn = Normal Cost
Cc = Cost Acceleration
Tn = Normal Time
Time After Accelerated Tc (Crash Time)